Theory of Constraints Handbook - James Cox Iii [33]
FIGURE 2-4 Seven problems with PERT/CPM management of single projects identified by Walker (1998).
Cause: Priority of resource use across projects may affect on-time project completion.
Cause: PERT/CPM does not provide priority rules to support project completion.
These are addressed by Guidelines VI, VIII, and XII.
Problem 3: Resource Contention across Projects Caused by Variability of Other Resources Figure 2-4 Problem 3 shows two simple projects diagramed as a single mega-project. Each project has only two activities. Only one activity (activity N in project 2) has any associated variability. Resource 1 is used by activity L1 in project 1 and by activity L2 in project 2 in immediate succession. Typical PERT/CPM calculations estimate the completion date of project 1 to be period 8, and the completion date of project 2 to be period 8. The dashed arrow in Fig. 2-4 Problem 3 shows the order of use of resource 1 as activity L1 then activity L2.
If all possible combinations of activity duration are enumerated, the completion date of project 1 is unaffected by the activity duration variability. However, when activity duration variability results in shorter than expected duration of activity N, a resource contention problem between activity L1 and activity L2 causes the delay of the completion date of project 2. Resource 1 is still in use by activity L1 when activity N is completed in period 2 (its optimistic estimate). As activity L2 cannot begin until activity L1 is completed, project 2 is unable to take advantage of an optimistic completion. A resource contention problem does not exist when activity N is completed in its pessimistic estimate. Therefore, only the late (pessimistic) duration time is added to the enumerated total, and the completion date of project 2 is later than planned. PERT/CPM does not recognize the impact of statistical fluctuation and dependent events on project completion. It should provide guidelines on buffering resources and paths against statistical fluctuations.
Cause: Murphy exists.
Cause: PERT/CPM does not protect against Murphy.
Cause: PERT/CPM does not recognize that multiple projects are interrelated due to the shared use of common resources.
These are addressed by Guidelines VI, VIII, and XII.
Problem 4: Resource Contention across Projects Caused by Variability of Common or Other Resources In Fig. 2-4 Problem 4, two simple projects are diagrammed as a single mega-project. The activity durations in project 1 are variable, while the activity durations in project 2 are deterministic. Resource X is used by activity X1 in project 1 and by activity X2 in project 2 in immediate succession. Typical PERT/CPM calculations estimate the completion date of project 1 to be period 8, and the completion date of project 2 to be period 12. The dashed arrow in Fig. 2-4 Problem 4 shows the order of use of resource 1 as activity X1 then activity X2.
If all possible combinations of activity durations for the two projects are enumerated, the completion of project 1 is unaffected by the activity duration